EnviroLoc 180C™ Website goes live.
EnviroLoc 180C™ website begins construction.
Comparative study completed on EnviroLoc 180C™ versus Traditional Liner such as High Density Polyethylene (HDPE).
EnviroLoc 180CTM versus Traditional Liner (HDPE) based on 96,000 sq. meters
| Construction Procedures | EnviroLoc 180CTM | Traditional Liner Direct Costs | Construction, Additional Days |
| Subgrade Preparation 95% | * Not Required (N/R) | $229,900.00 | 6 days |
| Bedding Sand 200mm | N/R | $507,840.00 | 8 days |
| Foundation Sand | N/R | $188,680.00 | 4 days |
| Foundation Pit 300mm | N/R | $55,650.00 | 8 days |
| Gravel 150mm | N/R | $479,770.00 | 5 days |
| ** $1,465,620.00 | 31 days |
* Based on the standard practice for HDPE of allowing only foot traffic on the containment system outside of the ring roads and access ramps. The EnviroLoc 180CTM System does not require compaction level of 95% for foot traffic. We only require removal of any sharp penetrations and a compact sand or natural clay substrate (using a Drum roller) with final grade for drainage.
** This does not take into consideration the additional Cost of cold weather installation, the EnviroLoc 180CTM system will stay flexible in temperatures as cold as -40°C/F eliminating any special winter heating or construction costs. These costs could run as much as $3.00 to $5.00 per square meter adding as much as $480,000.00 to the project costs.